Authorized by the Clarkstown Town Board · Feb 2025 – Jun 2026

$27,951,271

in new borrowing across 50 authorizations in 32 reviewed meetings. Refunding resolutions, which refinance existing debt rather than add to it, are excluded.

Counts only meetings whose bond lists an editor has reviewed and approved — a floor, not a complete census of town borrowing.

Largest single
$6.41M
Energy Related Improvements to Town Buildings
Median
$168K
Half are larger, half smaller
Authorizations
50
Across 32 reviewed meetings
Per meeting
$873K
Average across the set

Authorized by year

A year still underway is drawn hatched, because its total is incomplete by definition.

  • 2025$20.5M29 bonds
  • 2026$7.45M21 bonds · in progress

What borrowing this costs

The town has not published a rate or term for these authorizations — an authorization is permission to borrow, not a completed sale. Set the assumptions yourself and the figures below follow from them.

Interest rate
Term

Interest accrued since each was authorized

$971,726.85

Simple interest at 4.0%, counted from each authorization’s own meeting date to right now — about $3,063 a day at this rate. An estimate for scale; the town has not reported this figure.

Interest over a 15-year term

$8,944,407

Repaying $27,951,271.06 as a level-principal serial bond at 4.0% would add this much interest, for $36,895,678 repaid in total.

What the borrowing was for

Grouped automatically from the wording of each resolution. This is a reading aid, not an official classification — select a group to see exactly which bonds are in it.

Showing 10 matching bonds totaling $7,700,251.06 · Buildings & facilities. Clear search

Every authorization, by meeting

The record behind the figures above: all 50 bonds grouped by year and month, newest first. Each meeting date opens that meeting’s summary.

2026

2026 subtotal: $695,096.06

April 2026

Retain Tremco Roofing to Replace the Highway Department Roof at 12 Seeger Dr. Nanuet$79,096.06Apr 14, 2026
April subtotal$79,096.06

February 2026

Miscellaneous Minor Building Improvement Projects$250,000Feb 24, 2026
Traphagen Property Lead Abatement and Exterior Painting$200,000Feb 24, 2026
407 Storms Road, Valley Cottage Lead Abatement and Exterior Painting$166,000Feb 24, 2026
February subtotal$616,000

2025

2025 subtotal: $7,005,155

December 2025

Cul De Sac Building and PD Carport$39,900Dec 18, 2025
December subtotal$39,900

July 2025

Energy Related Improvements to Town Buildings$6,410,000Jul 22, 2025
July subtotal$6,410,000

June 2025

Asbestos Abatement at Town Hall Located at 10 Maple Ave, New City$35,000Jun 24, 2025
June subtotal$35,000

May 2025

Electrical Improvements to the Clarkstown Warehouse$116,230May 6, 2025
Mechanical and Plumbing Improvements to the Clarkstown Warehouse$204,025May 6, 2025
May subtotal$320,255

February 2025

Purchase of Seating and Related Upgrades for the Auditorium at Town Hall$200,000Feb 25, 2025
February subtotal$200,000